- (P10-46) A plant engineering group needs to set up an assembly line to produce a new product. The following table describes the relationships between the activities that need to be completed for this product to be manufactured:
Activity |
Days | Immediate
Predecessors |
||
a | m | b | ||
A | 3 | 6 | 8 | |
B | 5 | 8 | 10 | A |
C | 5 | 6 | 8 | A |
D | 1 | 2 | 4 | B, C |
E | 7 | 11 | 17 | D |
F | 7 | 9 | 12 | D |
G | 6 | 8 | 9 | D |
H | 3 | 4 | 7 | F, G |
I | 3 | 5 | 7 | E, F, H |
Assume that each activity time is normally distributed with expected time and standard deviation computed as shown in equations 7-6 and 7-8, respectively, on page 283. Round off all activity times to two decimal places.
- Use a Monte Carlo simulation to determine the probability that the project will finish in 37 days or less.
- Use a Monte Carlo simulation to determine the probability that the project will take more than 32 days.
Are you looking for a similar paper or any other quality academic essay? Then look no further. Our research paper writing service is what you require. Our team of experienced writers is on standby to deliver to you an original paper as per your specified instructions with zero plagiarism guaranteed. This is the perfect way you can prepare your own unique academic paper and score the grades you deserve.